The reorder point (ROP) tells at which level stock should be reordered. The idea is simple: after the order is placed, there must be enough stock to sell until the goods arrive, plus safety stock against the unexpected.
Formula
lead time demand (LTD) = daily demand × lead timereorder point = LTD + safety stockSafety stock has its own guide: How to calculate safety stock. The reorder point calculator gives both, along with the suggested order.
What the decision is based on: stock position
The reorder point is not compared with the stock on the shelf alone:
stock position = on hand + open purchase orders + transfers in transitorder needed ⇔ stock position ≤ reorder pointIf open orders are ignored, the same need is ordered again and again.
How much to order?
The reorder point answers “when”; “how much” needs a cycle quantity. Two common ways:
- Economic order quantity (EOQ): the quantity that balances ordering cost and holding cost. See the EOQ guide.
- Target cover: daily demand × target number of days (for example 30 days of need).
target level = reorder point + cycle quantityorder quantity = target level − stock positionThe quantity is raised to the minimum order quantity and rounded up to the case or lot size.
Example
Daily demand 10 units, lead time 14 days, safety stock 83.2 units. 150 units on hand, no open orders. Ordering cost 500, unit cost 40, annual holding rate 25%; minimum order 100 units, case size 50.
LTD = 10 × 14 = 140reorder point = 140 + 83.2 = 223.2stock position = 150 + 0 + 0 = 150 → 150 ≤ 223.2: order neededEOQ = √(2 × 3,650 × 500 / (40 × 0.25)) = 604.2target level = 223.2 + 604.2 = 827.4raw quantity = 827.4 − 150 = 677.4order = ⌈677.4 / 50⌉ × 50 = 700 unitsStock-out risk
If the stock position is below the lead time demand (140 in the example), stock runs out before the goods arrive even if the order is placed today. An order alone is then not enough; a transfer from another warehouse or expedited supply is needed. In the example the position is 150, so there is no risk, but the margin is only 10 units.
In VidiStock
VidiStock calculates the reorder point from the forecast for every product and warehouse. Lead time demand is built from the daily rates of the forecast periods (for example next month’s forecast divided by that month’s number of days), so a seasonal increase shows up in the reorder point in advance. On the Order Suggestions screen every suggestion has a step-by-step breakdown of this calculation; products whose stock position is below the lead time demand are flagged separately as “stock-out risk”.